ifcopenshell.api.sequence.assign_lag_time
¶
Module Contents¶
- ifcopenshell.api.sequence.assign_lag_time.assign_lag_time(file: ifcopenshell.file, rel_sequence: ifcopenshell.entity_instance, lag_value: str, duration_type: str = 'WORKTIME') ifcopenshell.entity_instance ¶
Assign a lag time to a sequence relationship between tasks
A task sequence (e.g. finish to start) may optionally have a lag time defined. This is a fundamental concept in construction scheduling. The lag is defined as a duration, and the duration is typically either calendar based (i.e. follows the working times and holidays of the calendar) or elapsed time based (i.e. 24/7).
A sequence may only have a single lag time defined. Negative lag times are allowed.
- Parameters:
rel_sequence (ifcopenshell.entity_instance) – The IfcRelSequence to assign the lag time to.
lag_value (str) – An ISO standardised duration string.
duration_type (str) – Choose from WORKTIME for the associated calendar-based lag times (this is the most common scenario and is recommended as a default), or ELAPSEDTIME to not follow the calendar. You may also choose NOTDEFINED but the behaviour of this is unclear.
- Returns:
The newly created IfcLagTime
- Return type:
ifcopenshell.entity_instance
Example:
# Let's imagine we are creating a construction schedule. All tasks # need to be part of a work schedule. schedule = ifcopenshell.api.sequence.add_work_schedule(model, name="Construction Schedule A") # Let's imagine a root construction task construction = ifcopenshell.api.sequence.add_task(model, work_schedule=schedule, name="Construction", identification="C") # Let's imagine we're doing a typically formwork, reinforcement, # pour sequence. Let's start with the formwork. It'll take us 2 # days. formwork = ifcopenshell.api.sequence.add_task(model, parent_task=construction, name="Formwork", identification="C.1") time = ifcopenshell.api.sequence.add_task_time(model, task=formwork) ifcopenshell.api.sequence.edit_task_time(model, task_time=time, attributes={"ScheduleStart": "2000-01-01", "ScheduleDuration": "P2D"}) # Now let's do the reinforcement. It'll take us another 2 days. reinforcement = ifcopenshell.api.sequence.add_task(model, parent_task=construction, name="Reinforcement", identification="C.2") time = ifcopenshell.api.sequence.add_task_time(model, task=reinforcement) ifcopenshell.api.sequence.edit_task_time(model, task_time=time, attributes={"ScheduleStart": "2000-01-01", "ScheduleDuration": "P2D"}) # Now let's say the formwork must finish before the reinforcement # can start. This is a typical finish to start relationship (FS). sequence = ifcopenshell.api.sequence.assign_sequence(model, relating_process=formwork, related_process=reinforcement) # Now typically there would be no lag time between formwork and # reinforcement, but let's pretend that we had to allow 1 day gap # for whatever reason. ifcopenshell.api.sequence.assign_lag_time(model, rel_sequence=sequence, lag_value="P1D")